Warsaw authorities have issued a new building permit for Warsaw One, a planned 188-metre skyscraper that will replace the Ilmet office tower in the Polish capital’s central business district. The decision, issued on 17 November 2026, advances a long-running redevelopment project by construction and property group Skanska, although work on the replacement tower has not yet been confirmed as underway.
The development is planned for 15 Jana Pawła II Avenue, beside Rondo ONZ, one of Warsaw’s principal business and transport intersections.
According to the official building permit notice published by Warsaw City Hall, the city approved the construction design and granted permission for a high-rise office building incorporating commercial premises, underground parking and associated infrastructure.
The decision, numbered 222/AM/WOL/PB/2026, was issued to Ori Development Sp. z o.o., a company belonging to the Skanska Group.
A 188-metre tower to replace Warsaw’s Ilmet building
Warsaw One would rise to a maximum planned height of 188 metres, substantially exceeding the existing Ilmet building.
Completed in 1997, Ilmet became one of the most recognisable office towers constructed during Warsaw’s post-communist commercial development.
Its distinctive architecture included a rounded section and, for many years, a rotating Mercedes-Benz emblem on the roof.
The building’s commonly reported height of 103 metres included the rooftop installation, which was removed in 2021. The main building structure measures approximately 83 metres.
Ilmet has 22 above-ground storeys and was designed by architects Miljenko Dumenčić and Mirosław Kartowicz.
The property occupies a prominent plot near Rondo ONZ metro station, surrounded by modern office towers and major commercial developments.
Skanska acquired the building in 2016, confirming at the time that the property would eventually be redeveloped.
In its original acquisition announcement, the company said the existing building offered almost 20,000 square metres of usable space.
The redevelopment is intended to replace this ageing office property with a significantly larger building suited to contemporary commercial requirements.
New permit follows years of planning
The Warsaw One project has a long development history.
Plans for a much taller replacement building emerged more than a decade ago, when the Danish architectural practice Schmidt Hammer Lassen prepared an early concept for the site.
Skanska subsequently acquired the property and continued preparations for its redevelopment.
The project received an earlier construction permit in October 2025.
The latest decision, issued on 17 November 2026, represents an additional administrative milestone for the proposed development.
According to specialist property publication Investmap, the new approval concerns Warsaw One’s planned office tower, commercial facilities, underground parking and supporting infrastructure.
However, the published municipal notice does not establish whether the latest permit is already final and beyond appeal.
It also does not confirm that construction of the new skyscraper has started.
The project’s investment value and a firm completion date have not been publicly established in the documentation reviewed.
Demolition preparations are already underway
Before Warsaw One can be built, the existing Ilmet tower must be demolished.
Preparatory work has been underway for several years, although the process has experienced interruptions.
In 2026, demolition activities resumed, including work to remove internal installations, fixtures and equipment.
As Architektura-Murator reported, Skanska had handed the building over for demolition-related work earlier in the year.
The redevelopment reflects a wider transformation of Warsaw’s commercial architecture, with a number of office buildings constructed during the 1990s being replaced or considered for redevelopment.
Older buildings may struggle to compete with newer properties offering more efficient floor layouts, modern building systems and contemporary environmental standards.
However, the eventual technical specifications and environmental certifications of Warsaw One will depend on the final development.
Why Warsaw’s office market matters for the investment
Warsaw remains Poland’s largest office market, with approximately 6.23 million square metres of modern office space at the end of the third quarter of 2026.
Recent market figures suggest that suitable centrally located office space is becoming more difficult to secure.
According to CBRE’s third-quarter 2026 Warsaw office market report, the citywide vacancy rate declined to 7.9%.
The central market was tighter still.
BNP Paribas Real Estate reported a vacancy rate of 4.3% in the city centre, compared with 4.8% in the narrower Central Business District.
No new office buildings were completed in Warsaw during the third quarter.
These conditions provide relevant commercial context for developers considering new projects in central locations.
A large office development near Rondo ONZ would add modern commercial space to an area where access to public transport and established business infrastructure can be important to prospective tenants.
Nevertheless, the market figures do not establish whether Warsaw One has secured occupiers, financing or a construction start date.
What happens next for Warsaw One?
The latest permit moves the project further through the administrative process, but several practical milestones remain.
Demolition of the existing Ilmet building must be completed before the replacement development can proceed on the site.
The investor must also finalise the necessary construction arrangements, including contractors, scheduling and any remaining administrative requirements.
No confirmed investment value, construction start date or completion deadline was identified in the latest official announcement.
For Skanska, Warsaw One represents an opportunity to redevelop a prominent commercial property in one of the capital’s most established office districts.
For Warsaw, it would mark another substantial change to the skyline that has developed around Rondo ONZ since the 1990s.
The immediate news is the new building permit — an important step for the project, but not yet confirmation that the 188-metre skyscraper is under construction.